A site diary: the five minutes a day that settles arguments

A short daily record made at the time is the most believable proof you can show in a dispute. Write down who was on site, what was done and what was agreed, and add a photo. It takes five minutes.

A bathroom half tiled, work in progress
A dated record of how the job looked on the day.

What to record each day

  • Date, and who was on site.
  • What got done, in a line or two.
  • Anything that held you up, and why: weather, a late delivery, no access.
  • Anything the client asked for or changed, in their words.
  • Deliveries, and anything wrong with them.
  • Photos.

Write it the same day. A note made at the time carries far more weight than one written from memory when there is already a disagreement.

Photos before you cover anything up

Pipes before the boards go on, cables before plastering, the damp you found behind the old units. Once it is covered, a photo is the only way to show what is there and that it was done right. It also helps the next trade, and you, if something needs fixing later.

Notes and photos go straight onto the job, and a weekly update goes to the client.

Try it free

No card needed

What it settles

ArgumentWhat the diary shows
"Why is it late?"Rain days, the late delivery, the week the client changed the layout
"I never asked for that"The day they asked, what they said, the photo
"That was already broken"Photos of how you found it on day one
"You never fixed the leak"Photo of the repair before boarding over

Keep it short and factual

Write what happened, not how you feel about it. "Client asked to move the sink to the window wall; will price as extra work" reads well to anyone. A rant about the client does not, and it may be read out one day.

Share it with the client

A short weekly update with the photos keeps the client in the loop, cuts the "just checking in" calls, and means they have seen the record all along. It is hard to dispute something you were sent every Friday. When the client asks for something new, agree it as extra work there and then.

A weekly update with photos sent to the client from JobGuard
The week's work and photos, sent to the client from the job.

Notes and photos go straight onto the job, and a weekly update goes to the client.

No card needed

Questions

Do I need a site diary on small jobs?

A few photos and a line a day is enough. The jobs that go wrong are rarely the ones you expected.

Are phone photos good enough as proof?

Yes, especially when they are dated and kept with the job rather than lost in your camera roll.

What should I write in a site diary?

The date, who was on site, what got done, anything that held you up, anything the client asked for or changed, deliveries, and photos. A line or two each day is enough.

Can a site diary be used as evidence?

Yes. A note made at the time, with dated photos, carries far more weight than something written from memory after a disagreement starts. It is not a guarantee, but it is the best record you can have.